Cadereaux of Uzès and the Limits in Nîmes
Razel-Bec, in a consortium with Franki Fondation, wins the contract for development work on the tunnel boring machine at Cadereaux d’Uzès and Limites in Nîmes.
The contract, worth 35 million euros, covers the digging with a tunnel boring machine of 2 cadereaux (980 m + 845 m) with an inside diameter of 3.3 m, the construction of the start shaft and the exit shafts as well as the realization of the hydraulic civil engineering in the works.